Thursday, May 28, 2009

Construction completed


Tuesday May 26 was a great day. Rocky Morin finished the last remaining section of boardwalk construction south of Maxwell Lake. There are still some new signs and metal brackets on the lake tower to come, but the boardwalk itself is complete. Thanks to Rocky and all the other volunteers this year we built the most ambitious of the 3 phases on budget and ahead of schedule.

Overall we now have 3 km of continuous boardwalk to enjoy, with main access from either the Sutherland Avenue or Reimer Drive trailheads. This completes the Beaver Boardwalk project. There are no plans to expand in the future.

If you haven't already checked out the new sections please give the boardwalk a visit. I'm sure you will be pleased.